Click here to reload our main page

PHONE: 07 3349 9104

MOBILE: 0413 004 014

Before & After
Concrete or Wood?
Deposits and Payment LAWS
Did you GET What You PAID For???
Excavations
Home
Our History
Questions?
Restumping
Retaining Walls
Steel Beams & Columns
Termites
Testimonials
The TRUTH about steel columns
Warning Signs
Copyright Notice

B.S.A. License Number: 68857

Contractor Links

Deposits and progress payments

...It has come to my attention from clients showing me other company’s contracts they did not accept, that many builders / house restumpers are asking for deposits of up to 50% and in one case there is a house raising and restumping contractor that demands a 50% deposit upon signing the contract!

One other case where I read a contract for restumping, he asked for 75% of the contract price to be paid - no less than seven (7) days before work starting!

On the 11th of May 2004 State Parliament passed the Building and Construction Industry Payments Act 2004

Your building agreement / contract (which may be a written quote that you accept in the case of smaller jobs valued at under $3300) should clearly state the payment arrangements, which you have worked out with the contractor (including specific amounts for the deposit and progress payments, if any and details of when these payments are to be made).

The Domestic Building Contracts ACT 2000 sets out maximum deposit percentages, which must not be exceeded, even if the home owner is agreeable.

If the contract is for domestic building work valued at $20,000 or more, the MAXIMUM deposit payable is 5%.

If the contract value is between $3300 and $20,000 the deposit MUST NOT exceed 10%.

Note: Although the legislation does not set maximum deposits for smaller building projects valued at less than $3300, the Building Services Authority (BSA), generally recommends no more than 20%.  Where the building work involves the construction of an entire home, the Domestic Building Contracts ACT also sets out an instalment schedule for progress payments. This schedule can be varied by agreement between the contractor and the home owner but it should not involve payment in advance of work progress.

Maximum Deposits:

The Domestic Building Contracts ACT 2000 provides that if the domestic building work is valued at $20,000 or more, the deposit must not exceed 5% of the total contract price. If the domestic building work is valued at more than $3,300 but less than $20,000, the deposit must not exceed 10%.

Note: although the Domestic Building Contracts ACT 2000 does not stipulate a maximum deposit for projects less than $3,300, the B.S.A. recommends no more than 20%.

These are the maximum deposits allowed under the Domestic Building Contracts ACT 2000.  You may negotiate and agree on a lesser deposit with your contractor, depending on a range of factors including how long the project will take to complete and what costs the contractor will incur (e.g. purchase of materials, preparation of plans, etc.) before commencing work.

It is an offence for a contractor to demand or receive a deposit, which exceeds the amount provided for in the Domestic Building Contracts ACT 2000.  Demerit points can be allocated against the contractor's licence for this offence.  If your contractor demands or receives a deposit in excess of that provided for in the Domestic Building Contracts ACT 2000, please notify the B.S.A.

For all other domestic building work valued at more than $3,300 but not involving the full construction of a home (e.g. renovations or extensions, concreting, sheds, kitchen renovations etc):

The maximum deposit percentages mentioned above still apply (i.e. not more than 5% for projects valued at $20,000 or more, and not more than 10% where the work is more than $3,300 but less than $20,000). In practice, it is customary on very small, quick jobs for all or nearly all of the money to be paid upon completion.

The progress payment arrangements (timing and exact amount) set out in your contract, should be directly related to work progress.  If the progress payment arrangements in your contract are not directly related to work progress, the contractor must give you a notice in accordance with Domestic Building Contracts Regulation 2000; Regulation 3, before you enter into the contract and you must initial the clause of the contract that sets out the progress payments.  If this does not occur, the contractor cannot demand or receive money not directly related to the progress of the work; It is an offence if the contractor does so and demerit points may be allocated against the contractor's licence. 

ü      Once work gets under way, stick to these contractual arrangements and never pay early or in advance of progress on the job.  

ü      Always inspect and check that the work is satisfactorily completed in accordance with your written agreement before making the final payment.

...If you pay any money before your job is started or even completed for that matter you’re being foolish in my opinion.  I would not pay any money at all before my job was finished and I would not pay a progress payment unless the job was half way finished and then would only pay a 10% progress payment.

Why, you may ask?  Easy answer: If a contractor takes on a job, he should have enough funds to cover that contract and all contractors have a 30 day account with suppliers, so knowing this, why do they ask for the payments before starting work and payments of up to half the contract price?

Back to Top

The following are actual copies of contracts I was given by clients, that verify what I say is correct:

Text Box: YOU MAY WANT TO TAKE NOTICE OF THE HIGHLIGHTED AREA WHERE IT STATES, "PAYMENT IS 50% ON COMMENCING..."
THE B.S.A. STATES THE FOLLOWING;
If the contract is for domestic building work valued at $20,000 or more the maximum deposit payable is 5%. 
If the contract value is between $3300 and $20,000 the deposit must not exceed 10%. 
(B.S.A. generally recommends no more than 20%)
The Domestic Building Contracts ACT sets out maximum deposit percentages, which must not be exceeded, even if the home owner is agreeable. 
 
 

Back to Top

Text Box: YOU MAY WANT TO TAKE NOTE OF THE PRICE;
...IT IS STATED THAT THE TOTAL PRICE IS $3,540.00 THEN YOU SEE THE "+ GST"; 
SO IT IS NOT A TOTAL PRICE, AS IF IT WERE, THE "+ GST" WOULD NOT BE THERE! 
SO WHAT IS THE REAL TOTAL PRICE?
:
$ 3,540.00 = SUBTOTAL 
+  $354.00 G.S.T.
= $3,894.00                       TOTAL PRICE OF JOB

 

Back to Top

...Same contractor as above, but I will point out just a couple of conflicts within his quote;

 

Text Box: The contractor states in his quote Number 5 "Remove old stumps from site", but if you read on it states; “For disposal of ANY existing stumps, owner to arrange for skip hire” extra cost to client, when the contractor should remove all rubbish from site and cost it into the contract.
Again, this contractor has made the price look cheap, by not adding the mandatory 10% G.S.T. 
$ 4,200.00 = QUOTED 'Total Price'
$ 420.00 = +10% G.S.T.
$ 4,620.00 = THE REAL TOTAL COST!
That price is the total only if he does not hire jackhammers @ $45.00 dollars per hour, If he does not have to load the skip, or do anything other than what the quote states.
 
 

 

Back to Top

Text Box: "PAYMENT IS 50% ON COMMENCING..."
THE B.S.A. STATES THE FOLLOWING;
If the contract is for domestic building work valued at $20,000 or more the maximum deposit payable is 5%. 
If the contract value is between $3300 and $20,000 the deposit must not exceed 10%. 
(B.S.A. generally recommends no more than 20%)
The Domestic Building Contracts ACT sets out maximum deposit percentages, which must not be exceeded, even if the home owner is agreeable. 
Is this contractor wise to go against the B.S.A. laws for payment?

Back to Top

Text Box: ...Only professional thing about this quote, is the printer who designed the quote form!  But I will give credit where credit is due; he did at least add the G.S.T. to the price...

Back to Top

 

Text Box: AGAIN; 
TAKE NOTICE OF THE PAYMENT REQUIREMENTS, IN PARTICULAR; 
"40% DEPOSIT DUE ON COMMENCEMENT"
 
Refer to the B.S.A. recommendations above.
 
The Domestic Building Contracts ACT sets out maximum deposit percentages, which must not be exceeded - even if the home owner is agreeable. 
 

 * Please also review our 'TRUTH about steel columns' section - where you will learn the difference between superior and inferior steel house columns...

Back to Top

 

...Over the past two years there has been an influx of house restumpers and house raisers and removers come into this trade. 

 

Just by looking in the local newspaper and in the yellow pages, I see the increase every week, but all of them are just builders with an open or restricted builders licence; none of them specialise in house restumping - THE most specialised trade, next to house raising, sliding and removal.  These new builders may know how to build a new pine framed home with a brick outer wall, but none of them know the old original 'Queenslander' home made from strong hard wood frames, yet these builders think just because they can build a home, they know all there is to know about house restumping! 

 

Well I do not think so for one minute, as there is a huge difference between a brick and tile home on a concrete slab on the ground, to a high set Queenslander on stumps!  If you intend to restump your home, would you want a general builder, OR would you want a person that is a specialist in the field; that being  HOUSE RESTUMPING ???

I know what I would want... 


Back to Top

Glenn Palframan House Restumping.
WebPages - Steve Mack. All rights reserved.
Revised: 09/12/11.

        Email Us Phone Us Fax Us        

Webpages - Steve Mack